Two schedules govern 6G: 3GPP's Release 21 ladder, and ITU-R's IMT-2030 submission window. They interlock with almost no margin.

Release 21, by plenary

QuarterTrackMilestone
Q2 2026
TSG#112
SA/CTRel-21 timeline agreed; TR 38.914 v1.0.0 approved done
Q3 2026
TSG#113
SA/CTRel-20 SA Stage 2 complete done
Q4 2026
TSG#114
RANRel-20 RAN1 functional freeze
Q1 2027
TSG#115
RANRel-20 RAN2/3 & RAN4-core functional freeze freeze
Q1 2027
TSG#115
SA/CTRel-20 Stage 3 freeze · Rel-21 package and 6G work items approved (Stage 1 freeze) freeze
Q2 2027
TSG#116
RANRel-20 RAN4 performance
Q2 2027
TSG#116
SA/CTRel-20 ASN.1 & OpenAPI freeze
Q3 2028
TSG#121
RANRel-21 RAN1 functional freeze
Q3 2028
TSG#121
SA/CTRel-21 SA Stage 2 complete
Q4 2028
TSG#122
RANRel-21 RAN2/3 & RAN4-core functional freeze freeze
Q4 2028
TSG#122
SA/CTRel-21 Stage 3 freeze freeze
Q1 2029
TSG#123
SA/CTRel-21 ASN.1 & OpenAPI freeze

Use the months, not the graphic

3GPP's published timeline graphic is good for structure — which track, which plenary, what freezes together. For a date, use the month-level table below, which comes from the "Timeline for Release 21" news item and the agreement documents RP-260868 (RAN), SP-260595 (SA) and CP-261259 (CT), agreed 10 June 2026 at TSGs#112 in Singapore.

MilestoneDate
Package approval + Stage-1 freezeMarch 2027
Stage 2, 80%March 2028
Stage 2 freezeJune 2028
Stage 3 freezeDecember 2028
ASN.1 / OpenAPI freezeMarch 2029

The ITU-R IMT-2030 clock

WhenMilestone
Nov 2023Rec. ITU-R M.2160 approved at RA-23 — the IMT-2030 framework
Oct 2024Circular Letter 5/LCCE/115 invites candidate RIT submissions; terrestrial window "02/2027–02/2029"
Feb 2026WP5D finalises draft technical performance requirements (Doc 5/116)
Jun 2026WP5D completes draft evaluation framework guidelines (Doc 5/119)
Dec 2026Study Group 5 approval of both
Feb 2027WP5D #54 — submission window opens
Feb 2029WP5D #59 — final deadline, 1600 UTC, 12 calendar days before the meeting starts

The interlock — our own arithmetic on verified dates

ITU-R's submission window opens February 2027, one month before 3GPP freezes Release 21 Stage 1 in March 2027. Its final deadline is February 2029, two months after Release 21 Stage 3 freezes in December 2028. That two-month gap is the entire margin in the programme.

M.2160's six usage scenarios, verbatim: immersive communication; hyper-reliable and low-latency communication; massive communication; ubiquitous connectivity; AI and communication; integrated sensing and communication.